Epoxy Injection of Original Cracks
The original plan involved partial chipping off of the pebble wash area only then do epoxy injection of the floors in the Overhead Tanks and Blowers area. However, as the contractor did the injections water comes out from underneath which indicated that the original waterproofing underneath may no longer be doing its job and the epoxy injections would be a waste. Further meetings resulted in expanding the project to chipping of 100% or the entire roof deck floor area.
20180322_102941
20180322_102951
20180314_094754
Update: Chipping works revealed what happened to the earlier epoxy injections
20180419_114320
20180419_114303 VIDEO